TotalEnergies, Partners Lift Force Majeure on Mozambique LNG Project
TotalEnergies and its partners have lifted force majeure on the 12.8 mtpa Mozambique LNG project, halted since 2021 due to security concerns. The revised plan targets first LNG cargo in the first half of 2029, with both trains completed by year-end. Final government approval of the updated budget and schedule is pending.